Industry News - Asian Oil & Gas Reports - Rankin beds in for NWS hub roleRankin beds in for NWS hub role from: Asian Oil & Gas by: David Morgan Thursday, August 24, 2006
If you're hoping for a spare bed on Woodside's 22-year old
North Rankin platform dream on. With platform drilling
currently under way, a raft of life extension and associated
field developments in the offing and its ongoing 'regional
hub' status now assured, all 145 of the platform's beds are
occupied and look set to stay that way for some years to
come. David Morgan reviews current activity and future plans
on the North West Shelf.
With projects completed or now in
execution adding up to a
commitment of some A$19 billion,
the North West Shelf remains Australia's
pre-eminent natural resource project -
and the springboard for operator
Woodside Energy's forays into the Gulf of
Mexico, West Africa and other far-flung
locations in recent years.
Woodside is one of six equal partners in
the North West Shelf Venture - the others
being BHP Billiton, BP, Chevron, Japan
Australia LNG and Shell - and it is
variously described within the Perthheadquartered
company as its 'backbone'
or 'heartbeat'. The North West Shelf
(NWS) accounts for some 75% of
Woodside's revenues, last year alone
generating overall project revenues in
excess A$10 billion and in turn
contributing A$1.2 billion in royalties
and taxes to federal and state coffers.
And with global LNG markets setting
the pace, and China's Guangdong
terminal having recently joined the NWS
Venture's traditionally Japanese and
Korean customer base, the race is on to
bring forth matching additional gas
supplies from the Woodside project
pipeline. Some of these projects, for
example phase one of the A$900 million
Perseus gas/condensate field development
and the A$1.6 billion Angel project,
which will include the NWS' third fixed
platform, are already committed and
advancing rapidly.
But there are plenty of other business
capture opportunities in the pipeline and,
with Woodside having contracted the
Ocean Bounty and Sedco 703 semis for
NWS work following a three-year
exploration drilling hiatus, the chances
are this list will be longer still by year-end.
The pace at which onshore gas demand
is currently pulling offshore projects
forward can be seen in the anticipated
doubling of the capacity of the NWS gas
plant near Karratha in little more than
five years. For more than a decade after
the 1991 start-up of its first three trains,
the plant's LNG production capacity
remained 7.5 million tonnes per annum
(mtpa). Today that figure is nearly 12mtpa
and by the end of 2008, following last
year's go-ahead for a A$2 billion fifth
train, it will rise to 16mtpa.
Woodside's North Rankin platform,
brought onstream in 125m of water in
1984, played a pivotal role in opening up
the North West Shelf resource and is now
set to do likewise as the hub for upcoming
developments in the area. Shrugging off
well-documented piling problems at the
installation stage attributed to the
region's tricky calcareous soils, the first
NWS fixed platform - it was joined by
Goodwyn about 23km to the southwest in
1995 - has performed admirably well over
its first 22 years. And life extension plans
now taking shape envisage Rankin
continuing in that successful vein for
another 30 years.
'We pride ourselves on some very high
reliability on Rankin,' enthused Dr Jack
Hamilton, looking back over his stint as
Woodside's director, North West Shelf
Ventures [he left the company mid-June
to become InterOil's president - see
'Appointments', page 52]. 'Despite its age
the platform still runs with an uptime,
including planned and unplanned, well in
excess of 98%.' Facilities were recently
added for remote monitoring of these
performance levels, which Hamilton
attributed to 'very close attention to
maintenance and very strong planning
functions'.
Even the substantial onboard integration
work associated with the
installation of the second NWS trunkline
- a hugely successful project in its own
right which came in A$113 million under
budget and ahead of schedule and late
last year won Australia's coveted Sir
William Hudson Award for engineering
excellence - left Rankin unfazed. 'With its
offshore and onshore components, that
72-hour shutdown was certainly the most
complex we had ever managed, but it was
done without missing a beat,' said
Hamilton.
Significant ongoing work is expected
on Rankin for the next five years, with
the conscious decision having now been
taken that Rankin will stay at the hub of
NWS operations and remain so to 2035.
Spending on Rankin life extension is
expected to be around A$300 million over
the next 3-4 years, probably approaching
A$1 billion over the next ten years and
embracing a whole series of investments
to enable Rankin to fulfil its hub role.
First up is work associated with the
NWS Venture's new Angel production
platform to the east, which will have
three subsea wells tied back to Rankin
via a new 50km subsea pipeline. About
A$150 million of the anticipated
A$1.6 billion Angel programme spend is
allocated to rebuilding the Rankin
control room, upgrading its control
systems and improving power generation
reliability, some of which Woodside
planned to do anyway and some because
Angel has now entered the equation.
Although relatively straightforward
structurally, Angel, unusually both for
Woodside and for a platform this size, is
designed to operate in normally
unmanned mode. Expected to be fully
operational by Q4 2008 in 80m of water,
the new platform will have drying and
dehydration facilities but power and
control will come from Rankin.
Hydrocarbons will be produced through
one processing unit with a capacity of up
to 800mmscf/d and up to 50,000b/d of
condensate. Angel's 7000 metric tonne (t)
topside will sit on a 7500t jacket secured
by eight drilled and grouted, piled
foundations, each weighing more than
3000t. (In July, J Ray McDermott landed
the US$200 million contract for Angel's
substructure and pipelay installation.)
Drilling of the three production wells is
scheduled between Q3 2006 and Q2 2007.
Angel will have one of the largest and
most complex process systems yet
employed on a normally unmanned
platform. Woodside will be looking to
develop a campaign of intervention to try
and build an uptime of greater than 96%
with periodic campaign maintenance. In
the early days one or two people will
probably stay onboard, but the plan is to
take them off and, using the limited
accommodation there for short bursts,
get it down to a monthly one-week
maintenance cycle after a couple of years.
Another activity occupying a good deal
of Woodside's attention at present - with
a view to arriving at the financial
investment decision (FID) late next year -
is the long-mooted Rankin sister
platform. North Rankin B (NRB) was
originally seen as a second production
platform but will instead be a
compression platform, bridge-linked to
NRA. Woodside, currently engaged in the
concept selection process and studying
compressor configurations, is now
contemplating an end-2011 start-up for
NRB. The topside floatover technique was
pioneered in Australian waters and is
now pretty well commonplace in the
world's more benign offshore operating
provinces. NRB is earmarked for
floatover too and at 20,000t-plus will come
close to the record for platform tonnages
installed this way.
Meanwhile, the drilling of three
extended reach wells from Rankin under
the Perseus 1B project should be complete
around September/October this year,
facilitating development of the southern
end of the Perseus field, a 1996 discovery
with estimated reserves of more than
280bcm, around 6km away. A bigger sister
project aimed at developing the northern
end of the field, and known as Perseus
over Goodwyn, is targeted for completion
mid-2007. This involves four subsea wells
tied back to the Goodwyn platform where
the gas will undergo preliminary
treatment before being piped to shore via
Rankin and the second trunkline. Those
two projects will almost see Perseus out,
save for maybe two or three more wells
under Perseus 1C currently envisaged for
late 2007.
Close to completion on the Goodwyn
platform, now out of gas recycle mode, is
the modification of one of its trains to
operate in low pressure mode. This too
has been a major challenge for an
operating platform, with Hamilton
declaring: 'We've kept the platform up at
98% onstream time despite a significant
reconfiguring of the train in the
workscope, and it's all been done safely.'
A short shutdown in May took care of
most of the remaining work on Goodwyn.
All that remains now is some tidying up
in terms of Goodwyn/Rankin interface
issues in readiness for late 4Q project
completion.
Another prominent gas target in
Woodside's opportunity portfolio is the
Western Flank, under which the
remainder of the NWS resource
southwest of Goodwyn would be
developed in three project phases at a
total cost in excess of A$1 billion. The
initial A$700-800 million phase,
provisionally scheduled for completion
around mid-2009, would see a pipeline
extending out to the southwest and the
development of between three and seven
subsea wells.
The total planned activity programme
around these committed projects and
some of the production opportunities
adds up to a spend close to A$10 billion -
A$8 billion offshore and A$2 billion
onshore - between now and NRB's
anticipated end-2011 completion.
Oil in the balance
Although gas has inevitably dominated
its activities in recent years, Woodside's
attempts to 'shift the balance a little bit',
in Jack Hamilton's words, have had a
measure of success both on the North
West Shelf and further afield. And in
pursuit of this oil the company is
developing world-class floating and
subsea production expertise.
FPSO-type production facilities have
become a particularly strong suit and by
the end of this year Woodside will have
four such vessels in service - Cossack
Pioneer which arrived on the North West
Shelf back in 1995, the Northern
Endeavour (at work in the Timor Sea
since 1999), Chinguetti, which started up
offshore Mauritania this February and
Nganhurra, due onstream at Enfield,
Australia's deepest water oilfield yet, in
Q4 this year - with a fifth - Vincent, in
1100ft of water off North West Cape in the
Carnarvon Basin - already sanctioned for
an expected 2008 start-up at an estimated
first-phase cost of A$1 billion.
Additionally, the company has a 50% nonoperating
stake in another Australian
FPSO-based development, BHP
Petroleum's Stybarrow.
Enfield, in which Woodside has a 60%
stake, is targeting about 100,000b/d
production, Chinguetti (Woodside 47%)
around 75,000b/d and Vincent (Woodside
60%) about 100,000b/d. With production
from its Laminaria field in decline, the
combination of these assets will add
much-needed lustre to Woodside's
recoverable oil reserves chart. They will
also have the benefit of Woodside's hardwon,
accumulated experience with its
first two FPSO developments over the
years.
According to Hamilton, the newbuild
Northern Endeavour has delivered
'exceptional reliability, in the first
quartile of benchmarking' in its remote
Laminaria field location in the Timor Sea
(AOG Jan/Feb 2000). Closer to home, the
long-serving and much modified Cossack
Pioneer, producing the Wanaea-Cossack
and neighbouring Lambert-Hermes
fields, continues to defy all projections as
to its likely retirement date. Given its
chequered early history - process issues
obliged Woodside to take the vessel out of
service for a major retrofit back in 1999 -
Cossack Pioneer qualifies at best for an
'average' benchmark in today's overall
reckoning of comparative FPSO
performance and reliability. Recent
production levels of the order of 120,000-
130,000b/d paint a rosier picture, however.
When Cossack Pioneer was put into
service 2P reserves of 245 million barrels
were expected; by the end of last year it
had produced 320 million barrels and
there was still believed to be some 225
million barrels to go.
With Laminaria's output through
Northern Endeavour now down to around
20,000b/d compared with its 180,000b/d
peak, Woodside admits that opex is now a
'very strong feature' of this FPSO activity
and reckons it has already taken almost
50% of the routine operating cost out of
Northern Endeavour.
Cossack Pioneer on the other hand is
actually still running at or near full and
the company sees things staying that way
probably through to 2009. So at the
moment the accent is on managing
Cossack Pioneer's costs sharply but still
on the basis of maintaining reliability;
the question of actually sacrificing
reliability for cost benefit in a trade-off
has yet to arise. At Laminaria, on the
Northern Endeavour, however, those
'considered trade-offs' are being made
because of the capacity catch-up.
Recent studies undertaken by Woodside
are expected to yield a decision in 3Q this
year on Cossack Pioneer's likely life
extension requirements. Modifications
are already under way to accommodate
gas compression/gas lift around the
Hermes field. In addition, some 'two to
three years of infill opportunity' are
anticipated in the vicinity of Wanaea-
Cossack. Field life at Cossack is going out
to at least 2019 and the company is
working out its strategies for running out
to that duration.
Woodside's resumption of exploration
drilling this year follows in the wake of a
3D seismic shoot which, for a few weeks
at least in 2003 until the intervention of
Chevron's Gorgon project, lay claim to
being the southern hemisphere's largest.
With the aid of the drill bit, Woodside
now has its sights set on moving a mix of
both gas and oil prospects into its
regional production opportunities
portfolio. The latter already includes a
potential 60-80 million barrels
recoverable NWS Western Flank oil
development around the Dixon discovery,
where appraisal drilling got under way in
May in preparation for what is seen as a
'make or break' development decision. It
will likely be joined by others this year as
NWS prospects such as Pemberton and
Persephone, both gas, and Homer East
(oil), take their turn in the E&P crosshairs.
Set for subsea
One recent organisational consequence of
Woodside's growing mix of production
facilities at home and abroad has been
the creation of a specialist subsea
function within the company.
On the North West Shelf, the company
currently has seven subsea wells but that
figure is expected to climb above 23 by
around 2012. Woodside has a frame
agreement with FMC Technologies for
the supply of trees, an arrangement
which is reported to be working well and
offers plenty of upcoming scope.
The recent reorganisation, bringing
together subsea engineering expertise
previously scattered throughout the
company, is 'all about looking forward
and recognising the benefits of pulling it
together as a discipline', explains
Woodside. 'With the amount of subsea
production we'll be operating, in
association with FPSOs and fixed
platforms, this is becoming a core
activity for and we need to focus on it.' AOG
Click here to register to receive your own copy of Asian Oil & Gas each month.
|