Industry News - Asian Oil & Gas Reports - The key to unlocking KikehThe key to unlocking Kikeh from: Asian Oil & Gas by: John Mueller Thursday, August 24, 2006
Kikeh, Malaysia's first deepwater development, will boast both the first spar platform
outside the Gulf of Mexico and the premier application of a tender assist drilling unit
(TADU) with a spar. John Mueller reviews the thinking behind this novel combination.
The spar platform, in service in the
Gulf of Mexico since 1996 for
production only and fully integrated
production and drilling operations in
water depths ranging from 1900ft to
5600ft, will now be introduced to
Southeast Asia with the Kikeh spar
wellhead platform, to be positioned in
4364ft of water.
The Kikeh spar will support a dry tree
unit riser system with a TADU for field
development drilling, connected by a new
tandem mooring system.
The Kikeh spar design is being
undertaken on four continents and
coordinated in Kuala Lumpur, Malaysia,
where the hull and topsides are also being
constructed. The spar configuration,
fabrication methodology and field
installation plans were developed by
Technip technology centres in Houston,
Perth, Paris and Pori, Finland, with
technology transfer to Malaysia project
management.
Hull transport to the Kikeh field will be
via a combined dry and wet tow
operation, with topsides installation at
the Kikeh location by floatover.
The match of a TADU and spar-based
dry tree unit is a first case application
that poses the challenge of designing a
tandem mooring system to control the
relative movement of the two vessels
during various conditions such as the
TADU rig-up phase, normal operations
and pull-back mode in extreme
environmental situations.
Spar bright
The spar concept has evolved through
application entirely in the Gulf of Mexico.
Kikeh is employing a truss spar, which
essentially consists of a cylindrical,
compartmented upper section, the hard
tank, for buoyancy and a lower section
composed of a space frame truss with
several fully plated horizontal levels,
known as heave plates, to trap the mass of
entrained water in a wave surge. Also, at
the bottom of the truss, is a soft tank, a
plated-steel structure that provides
buoyancy at the keel when the spar is
towed out in a horizontal position. The
soft tank includes compartments for high
density fixed ballast, which is added
offshore. This configuration results in
very low heave and pitch motions in
extreme weather conditions.
Variable seawater ballast in the bottom
of the hard tank adjusts draft and trim for
major variations in topside loading, as for
a top tension riser.
Superior floating stability results from
the centre of gravity being located well
below the centre of buoyancy, without
reliance on the mooring system, allowing
installation of top tension risers with dry
trees.
Drilling from a spar platform is unique
in the sense of being able to have the
drilling riser permanently installed
during development drilling. This is
achieved by utilising a dedicated drilling
slot on the spar and incorporating a
drilling riser parking position on the
seabed. This means that the drilling riser
does not have to be pulled when running
production riser or completing wells.
The spar hull and topsides for the
Kikeh field, held by Murphy Oil
Corporation (operator) and Petronas
Carigali in a 80:20 venture, are being
fabricated by Malaysia Marine & Heavy
Engineering (MMHE) at its yard in Pasir
Gudang, Johor, about 800 miles from the
project.
The contract for the dry tree unit
engineering, procurement, installation
and commissioning was awarded to
Technip Marine (Malaysia), with
construction at MMHE.
The Kikeh development, situated in the
southern part of Malaysia's block K - and
its first deepwater discovery - has a
recoverable reserve base in excess of
400 million barrels. The spar will be
delivered to the Kikeh field in late 2006
with first production expected in 2007.
The truss spar hull will have a
diameter of 106ft, overall length of 465ft
and draft of 430ft. The payload of 10,500t
includes the topside, risers and the
drilling/workover rig.
The seabed well pattern for Kikeh
consists of a circle 156ft in diameter while
the well slots on the platform are located
in a five by five configuration with an 11ft
spacing. The spar has 24 slots arranged in
a circular layout for production/water
injection risers and a dedicated centre
opening for the drilling riser. When
drilling wells, the whole spar moves over
the subsea wells to achieve alignment. In
tieback mode, the drilling equipment set
is skidded over a surface well location
and the spar positioned to align the
surface well slot, with drilling equipment
set, and the subsea well.
An API standards spread mooring
system will be made up of 10 lines of
chainwire-chain in four groups, designed
to handle extreme 100-year conditions
with a single mooring line failure.
The Kikeh spar will utilise the Smedvig
semisubmersible West Setia to provide
tender assist drilling services for field
development for two drilling periods of
about 39 months and 24 months. West
Setia, a two pontoon and six-column semi,
has cranes for lifting the self-erecting
DES on to the spar in several packages,
weighing up to 240t.
A personnel gangway will be provided
between the spar and TADU.
The West Setia will be moored to the
seafloor by four mooring wires from four
winches and fairleads on its aft columns
and connected to the spar using a fourline
lashing system.
Nylon hawsers will provide stretching
capability to absorb the relative motions
between the TADU and the spar, mounted
vertically along the hull of the spar.
Model tests for the Kikeh spar were
conducted at Force Technology in
Denmark in two campaigns, testing the
spar alone and with the TADU in close
proximity for several environmental
headings and for a number of one-year, 10-
year and 100-year wind, wave and current
events. In total, more than 100 different
cases were tested.
Compared to a subsea development
with wet trees, a spar-based dry tree
wellhead platform provides many
benefits. A wet tree requires expensive
subsea flowlines, and more costly risers
and subsea trees than dry tree
completions. In addition, the wet tree
drilling operations have to be carried out
by a mobile offshore drilling unit
(MODU) with limited availability and
high dayrates which not only impacts
initial drilling but also subsequent well
activities, typically resulting in fewer
interventions and consequently less total
oil recovery.
Drilling from a spar is more efficient
than from a MODU resulting in a spar
requiring fewer days to drill and
complete each well. A single derrick
MODU, for example, has to run and
retrieve the drilling riser between each
well whereas a spar does not.
For a large drilling programme, 20
wells in the case of Kikeh, high MODU
dayrates and additional days per well
result in a wet tree drilling Opex that is
substantially higher than the Capex plus
Opex for a spar supported drilling
system.
A further advantage with a spar dry
tree unit is the higher overall oil recovery
as a consequence of having lower-cost
direct access to the subsea trees.
Economic analysis demonstrates that, if
the aerial extent of the reserves permits
drilling from a single location, a spar dry
tree unit is more cost effective than a wet
tree development requiring a MODU.
Regional choice?
The Kikeh spar may be an optimum
deepwater drilling and production
system for Southeast Asia.
Prior to Kikeh, the concept of spar
drilling took one of three approaches:
A pre-drilled MODU phase using a
completion rig on the spar to tie back and
complete the dry tree wells.
Offset drilling where drilling is done by
a MODU, with both the MODU and the
spar on site, and final tieback to the spar
is by a spar borne completion unit.
All development drilling done by a full
size drill rig integrated into the spar
topsides, with possible pre-drilling from a
MODU.
The Kikeh project, on the other hand,
adds a new spar drilling and completion
option by employing a TADU for the
development drilling phase and a lighter
spar supported drilling unit for future
workover operations.
For the cases with MODU sustained
development drilling, the spar is not
designed to bear the full drilling package
payloads, which saves on spar hull and
mooring Capex. However, because of high
dayrates, a wholly deepwater MODU
development drilling regime increases
Opex.
Furthermore, availability of MODUs
may also impact the flexibility of a
drilling programme.
For the case of an integrated drilling
system on the spar, the spar hull has to
hold the weight of a full size drilling rig
including drilling consumables, power
generation, and crew accommodation.
This calls for a larger hull and mooring
system and increases spar system Capex.
A fully integrated spar drilling system,
compared to the TADU method, requires
about three to four times the payload and
around four times more deck area for
drilling, necessitating an increase in spar
hull diameter from 106ft to 124ft along
with greater hull weight. In addition, this
option will also include the cost of
retaining the drilling equipment and
drilling support systems, which usually
remain on the platform over the lifetime
of the field.
The integrated Kikeh solution allows a
more flexible drilling programme,
combining aspects of the three previous
spar drilling techniques.
The Kikeh spar hull and mooring
systems are designed to withstand a
maximum drilling load of about 1850t
while the rest of the development drilling
payload is maintained on the TADU. For
future workover operations, the Kikeh
spar will carry a smaller workover rig
with a total drilling payload of about
2000t. Consequently, there is no penalty
for supporting the DES in the
development phase. In addition, the selferecting
tender rig is contractor owned
and removed after the development
drilling campaign and does not impact
the operator's upfront investment. AOG
This article is based on a paper by
Technip and Smedvig to this year's
Oceantex conference in Mumbai, India.
Click here to register to receive your own copy of Asian Oil & Gas each month.
|