Industry News - Asian Oil & Gas Reports - Moving storyMoving story from: Asian Oil & Gas by: Terry Knott Friday, October 27, 2006
For the onshore lifting of the Lun-A deck,
main topsides construction contractor
Samsung contracted heavy lift and
transportation specialist Fagioli PSC.
The operation, the first stage of which
was performed in April this year, involved
moving the deck from a multipoint
support in the yard to a four point
support, in readiness for jacking the deck
up by 24m. This allowed the insertion
below of the loadout support frame (LSF)
for transportation to the field by barge.
Intermediate weighings of the massive
deck structure carried out during the
moving operation put the deck weight at
23,500t.
The Lun-A deck required 52 L600 jacks
for weighing and the same number were
used for the lifting of the deck. A
multinational Fagioli PSC team, working
in back-to-back 12 hour shifts under
overall control of Fagioli PSC UK
engineers, carried out the lifting
operation. The jacking system was
computer controlled remotely from a
central control cabin. During periodic
breaks in the lifting operation to enable
Samsung to add new leg can sections, the
LSF skidding system was set up by
Fagioli, comprising a single L600 jack on
each of the two skid tracks along with a
60m-long, 37-strand pulling cable. Each of
the jacks was driven by a dedicated
L2/70D power pack to give a skidding
speed of around 12m/h. The power packs
were controlled locally at built-in control
consoles, in radio communication with a
Fagioli PSC supervisor who guided the
LSF along the skid tracks.
On completion of the LSF skidding
operation and the placement of bearing
pads by Samsung, the Lun-A deck was
gently lowered to transfer all load onto
the LSF. Next came the setting up of the
loadout skidding system, consisting of ten
L600 jacks, six on the deck's east
skidtrack and four on the west, along with
165m-long, 37-strand pulling cables. Each
pair of jacks was driven by a dedicated
L2/70D power pack to give a skidding
speed of
12m/h,
with all
jacks and
power
packs
connected
to the
central
computer
control system. The LSF and deck were
thus moved from the yard onto the
transportation barge.
Later this year, the topsides for Lun-A's
companion platform for the Sakhalin
project, PA-B, will be also be lifted
through 24m at the yard, and could weigh
as much as 31,00t. AOG
Click here to register to receive your own copy of Asian Oil & Gas each month.
|