Industry News - Offshore Engineer Reports - Deep developments taking shapeDeep developments taking shape from: Offshore Engineer by: Marshall DeLuca Wednesday, September 01, 2004
In recent months, deepwater development activity in Brazil has
been hotter than any other place in the world with several major
pieces of Petrobras's plans moving into place and contracts
being awarded for many others. Marshall DeLuca provides the
latest update on the action.
Presently there are seven major
projects underway offshore Brazil
in some stage of development, all
operated by Petrobras. In the short period
of time since the last report (OE April
2004), all have experienced significant
levels of activity including several new
projects out for tender, new major
contracts awarded and new systems
entering production, thus further
illustrating why the country continues to
be a dominant player in the world
deepwater E&P game.
The latest on the Brazilian deepwater
developments underway or planned for
the near term include:
According to the original plan, Albacora
Leste, the eastern sector of Petrobras's
massive Albacora Campos Basin field,
was expected to be onstream by now, but
due to shipyard delays with the FPSO
P-50 that will serve as the centerpiece of
the development the project is running a
year behind schedule.
The vessel left Singapore's Jurong
Shipyard the second week in July headed
for the Mauá Jurong yard outside of Rio
de Janeiro. Jurong converted P-50 into an
ABS-classed 180,000b/d of oil and 6
million cm/d capable FPSO from the
280,000t VLCC Felipe Camarao, marking
the yard's sixth completed floater for
Petrobras to date.
Both shipyard and operator have
admitted to a share in the blame for the
delays and related cost overruns
resulting chiefly from job scope increases
and design changes and have worked out
their differences through re-negotiations
of the contract.
P-50 is expected to arrive in Brazil this
month where it will undergo topsides
integration and commissioning at Mauá
Jurong which fabricated the modules.
Upon completion the vessel will head to
the field where it will hook to 15
producers and 15 water injectors. Peak
production is expected to be 164,000b/d
reached in 2009.
Halliburton continues to struggle with its
dual-FPSO Barracuda-Caratinga EPIC
project for Petrobras. Most recently in
June the company, through its KBR
subsidiary, announced the project is
experiencing further delays primarily
attributed to what the company says is a
significant reduction in shipyard
subcontractor productivity in completing
the projects in Brazil as well as some
rework identified during the integration
of the modules onto the vessels. As such,
Halliburton took an additional pre-tax
charge in the second quarter of about
$200 million as a result.
The project involves two ABS-classed
FPSOs converted from VLCCs and renamed
P-43, destined for 2600ft of water
on Barracuda, and P-48 that will produce
Caratinga in 3400ft of water. Both are
capable of storing two million barrels
and processing 150,000b/d of oil.
Final work on the two vessels is
underway at the Mauá Jurong yard for P-
43 and BrasFELS for P-48 and has been
increased to an accelerated pace.
Petrobras said it expected P-43 on
location on Barracuda this month with
P-48 onsite on Caratinga in November
and both platforms fully operational
before the end of the year.
Petrobras added that the delays are the
responsibility of KBR. It said this
reduced productivity mentioned by
Halliburton is mainly because of the
failure of KBR to deliver materials
required to allow the shipyards to
complete mechanical work on platform
systems within the completion schedule.
The two companies are continuing to
work towards finalizing an agreement in
principle that would resolve certain
contract issues and establish revised time
frames and penalty clauses in order to
provide better and more precise
conditions for concluding the work.
Once onstream, Barracuda is expected
to produce a peak of 146,000b/d of oil
with 34 wells (20 producers, 14 water
injectors) while Caratinga will peak at
127,000b/d with 20 wells (12 producers
and 8 water injectors).
Reports out of Rio indicate Petrobras is
in the process of fast-tracking development
on its 2003 Golfinho light oil
discovery in the Espirito Santo Basin.
The plan calls for a leased FPSO set in
between 4000ft and 4500ft of water
producing from around four to eight wells
at rates of 100,000b/d of oil and 4 million
m3/d of gas.
Petrobras invited companies to tender
for the FPSO contract in May with an
award likely by the end of the year if
approved by state regulator ANP. If it
holds to this schedule, first production
would occur by year-end 2006. The field
has estimated reserves in the 250 million
boe range.
In July, Brazilian engineering firm GDK
Engenharia began work on the first of
two Petrobras projects named for a local
whale breed, Jubarte, a 600 million barrel
heavy oil find discovered in January 2001
located in the extreme north of the
Campos basin.
Due to the heavy oils found in the field
(17°API), Petrobras initially was unsure
of the field's commerciality, the challenge
being how to produce the oil using subsea
completion and electrical submersible
pumping as the artificial lift. As such, in
December 2001, the company embarked
on a pilot project centered on an extended
well test using a 950hp ESP installed
directly above a subsea tree producing to
the Seillean FPSO which was modified to
handle the heavy crude. Since that time
the project has shifted to a long duration
test and the well has reached a peak of
22,700b/d making the field the first in the
world to produce this type of crude.
With this success, Jubarte was declared
commercial in December 2002 and the
first phase of production is expected by
the second half of next year. The
development calls for four wells to
produce to P-34 FPSO, presently under
modification at GDK to upgrade the
processing unit and extend the mooring
capability from 2600ft to 4400ft. The vessel
was previously stationed on the
Barracuda field before being removed
after nearly sinking in 2002. When
complete the vessel will be renamed
Juscelino Kubitschek in homage to a
former Brazilian president and capable of
producing 60,000b/d.
A second phase using another FPSO is
also being planned for a 2009 startup. This
will involve 21 producing wells, six
injection wells with production expected
to be in the 150,000b/d range.
Petrobras is also undergoing development
planning for its second whale
project, the neighboring Cachalote. The
field was discovered in November 2002 in
4800ft of water with reserves in the heavy
crude range of 19°API and about half the
size of Jubarte. The field was declared
commercial in December 2002 and will be
developed through a single phase using a
floating production unit producing six
wells with four water injectors.
Production is expected to average
between 50,000b/d and 75,000b/d.
Bidding for contracts relating to P-53, the
FPSO that will produce 180,000b/d on the
Marlim Leste field, were finally
submitted to Petrobras in late May after
months of delay within the state-owned
operator. A call for bids on the EPC
contract was originally opened in late
November and was expected back in
February, which was again postponed
until 31 May due to problems with the
government over the oil export line for
the project.
The tender calls for conversion of
VLCC Settebello into the FPSO and
construction of topsides. The vessel will
be set in 1100m of water and fitted with a
monster-sized turret capable of
accommodating 75 risers.
Several companies have bid on the
project including the Jurong Shipyard in
Singapore which has worked on several
Petrobras floater projects, as well as three
Brazilian groups. While no timetable has
been announced for award, reports
indicate it could come as early as this
month.
Some contracts have been let, however.
Dresser-Rand has won the rights to
supply the gas compression module while
Rolls-Royce will provide the power
generation.
Marlim Leste will produce from 15
wells with nine water injectors connected
to the FPSO through flexible lines. The oil
will be transported to shore via pipelines
while gas will be sent to P-26 in the
Marlim field. Production is expected to
commence in the second quarter of 2007.
On 7 June Petrobras began production on
the FPSO Marlim Sul, a 1.6 million barrel
capacity converted VLCC that is being
used for what the company calls the
'Complementary System' of Module 1 of
the Marlim Sul field.
The Marlim Sul field which has been in
production since April 1994 is presently
in the first of a planned four-phase
development.
This first phase, called Module 1, began
production in December 2001 using P-40
semisubmersible to produce 16 wells
with10 water injectors averaging flow of
150,000b/d.
However, due to excellent productivity,
Petrobras decided to enact the
Complementary System that would add
five oil producers and four water
injectors to the development at a rate of
100,000b/d.
To accommodate this additional
production the company leased the FPSO
Marlim Sul from SBM for an initial term
of seven years and ten months. Keppel
FELS performed the conversion and the
unit is equipped to process 100,000b/d of
oil, 2.3 million m3/d gas lift and water
injection of 125,000b/d.
Peak production is expected to be
reached before year-end.
In the meantime, contracts have begun
going out for the second phase - Module
2. This plan will use a semisubmersible
production unit, P-51, the first built
entirely in Brazil, set in 4100ft of water
capable of producing 180,000b/d of oil
and 6 million m3/d of gas from around 14
producers with 10 water injectors
beginning in the first quarter 2008.
A consortium of Fels Setal and Technip
Engenharia have won the $639 million job
to build the 41,000t platform. According to
the plan Keppel Fels in Singapore will
build the corner nodes of the lower hull,
a portion of the lower hull will be
subcontracted to the Brazilian Nuclep
yard and Fels Setal will build the
remainder of the lower hull, deckbox,
topside, accommodation and modules as
well as perform the commissioning.
Technip will be responsible for the
overall engineering and detailed
engineering of the deckbox and offshore
mating and transportation.
Construction is expected to take 47
months.
Additionally, Kvaerner Oilfield
Products has won the $16 million contract
to supply 11 GLL2000 subsea trees for the
job. The trees are rated for 2000m water
depth operation and delivery is expected
next year.
Expansion of the giant Roncador field is
beginning to take shape. Late last year
Petrobras awarded a consortium of Fels
Setal and Technip a contract to fabricate
a new 80,000t displacement semisubmersible
FPU, P-52, that will be set in
5900ft of water with capacity to produce
180,000b/d of oil. This new facility,
expected on location in August 2006, is
part of the second phase of the field's
Module 1A development plan.
The first phase of Module 1A presently
has the field producing from eight wells
with three water injectors to FPSO
Brasil, brought in to fill the void left
vacant with the P-36 tragedy. This second
phase will increase the well count to 20
producers and 10 injectors when brought
onstream in early 2007. Once all the wells
are tied in, FPSO Brasil will then depart
the field, which is expected to occur
sometime the following year.
Work has now begun on the next phase
of the development, Module 2. In early
June Petrobras awarded Jurong Shipyard,
which has performed six floater
conversions for the company since 1997,
the $628 million EPC contract for the
conversion of the 280,000dwt VLCC Barao
De Mauá to an FPSO, P54.
The vessel will have capacity for
180,000b/d of oil, 6 million m3/d of gas
and 39,000m3/d of water injection.
Production will come from 13 wells and
eight water injectors all connected
through flexible risers via an external
portside balcony with export sent
through a 10in flexible riser connected to
the portside. Additionally the unit will be
moored in 4300ft of water using
Petrobras' DICAS spread mooring system
with 20 miles composed of chain/
polyester/chain segments.
Work began on the vessel last month
and is expected to last 38 months. The
work is taking place in both Singapore
and at the company's yard outside of Rio
similar to the plan in use for P-50 being
completed for Albacore Leste.
FMC has won the order to supply
subsea production equipment for the job
that includes manifolds, production
controls and associated equipment, while
the installation contract is expected to be
awarded shortly. A further two modules
are being studied for the field for the
future. OE
Click here to register to receive your own copy of Offshore Engineer each month.
|