Industry News - Offshore Engineer Reports - Back from the brinkBack from the brink from: Offshore Engineer by: Rick von Flatern Monday, August 01, 2005
On Friday 8 July,
commissioning crews
onboard the BP Thunder
Horse platform moored in 6050ft
of water in the Gulf of Mexico's
Mississippi Canyon 778, 150
miles southeast of New Orleans,
went through abandonment
procedures and departed the
installation ahead of the arrival
of Hurricane Dennis. By the
following Monday morning the
world's largest semisubmersible
production platform was listing
at an estimated 20°, one corner
of its topsides beneath the
water's surface.
While none of Thunder
Horse's wells were in
production or had been tied
back to the platform at the time
of the abandonment, three
subsea trees had been installed
on live wells located on the
seafloor directly beneath the
platform.
Within the week BP had
turned over responsibility for
bringing Thunder Horse right
again to Rotterdam-based Smit
Salvage. At one point, as many
as 700 personnel and 15 vessels
including Heerema's massive
Balder deepwater construction
vessel, were dispatched to the
area and another 200 BP
personnel were providing
engineering and technical
support from the company's
Houston office.
By 19 July, as OE went to
press, BP spokesman Ronnie
Chappell confirmed that
pumping efforts had restored
the vessel to normal trim,
freeboard and displacement,
and all but residual water had
been evacuated from the hull's
two flooded columns. BP and
Smit were continuing to make
the platform seaworthy and
storm-safe as a precaution
against changes in weather
conditions due to Hurricane
Emily entering the western
Gulf of Mexico.
But even as the good news of
Thunder Horse's righting
continued to come in, what
caused its columns to flood
remained a mystery. The
hurricane, according to a
nearby buoy, created no waves
larger than 30ft, far too small to
affect the massive structure's
stability.
With BP unable to explain the
event, speculation in the media
and elsewhere seemed to center
on improper crew abandonment
procedures or automatic
ballasting system failure.
Analyzing the former, if it is
indeed considered, would take
considerable time and an
answer could be long in coming
and likely subject to interpretation.
The latter event seems
unlikely as during abandonment
the main generator is left
shut down with only an
auxiliary generator left online
to control navigation aids such
as horns and lights. The
smaller generator cannot
provide sufficient power to run
the ballasting systems.
During recovery operations,
BP reports, all possible sources
of water ingress along the hull
were covered and no breaches
of the hull were found during
ROV-based inspections.
At one point, while pumping
water from the columns, the
company cut one of the 16
mooring lines to determine if
that would hasten the vessel's
righting. But once done,
Chappell said, the company
decided to focus on the
pumping operations.
With the vessel now at
normal trim, the company will
attempt to discover the causes
of the near-disaster and the
extent of the damage. Depending
on the outcome of that
investigation, BP will decide if
the semi must be towed to
shore for repairs. Assessment
of topside damage, if any, had
yet to be begin as OE went to
press, engineers at the scene
having had their hands full
directing recovery operations.
The field was expected to be
onstream by the end of the
year. The semisubmersible was
installed on location in late
May and was beginning
hookup procedures prior to the
evacuation. BP is 75% owner of
Thunder Horse with Exxon-
Mobil holding the remaining
25% interest. OE
BEFORE AND AFTER: (photos below)
The 59,000t Thunder Horse semisubmersible, the world's largest, was found to be listing approximately 20 degrees on 11 July
(pictured top) following evacuation from Hurricane Dennis. By 19 July, after a joint effort spearheaded by BP, the US Coast
Guard and the Minerals Management Service and involving more than 900 personnel, the platform had been returned to its proper trim.
BP is still investigating the cause of the incident.
Photos courtesy of BP, LEWCO Systems and USCG.
Click here to register to receive your own copy of Offshore Engineer each month.
|